250,000-Tonne Electrical Steel Project Accelerates at Full Throttle

2025-04-30

In the deep spring of April, construction is in full swing. The construction site of Jinlei's high-grade electrical steel new material project is in full swing, and the crane is roaring. Everywhere one could see the busy figures of construction workers, measuring scales, tying steel bars, and moving materials, each task being carried out intensively. The following is the progress report of the project in April.



Overview of project progress



01 Steel Structure Progress


The overall construction progress has been completed by 60%, and the specific progress is as follows:


350 steel columns have been completed;


520 crane beams have been completed;


246 roof truss beams have been completed;


52% completion of roof purlins;


50% completion of wall purlins.



02 Equipment infrastructure construction


The excavation of the foundation for rolling mill 2 # 1400 has been completed.



03 Progress of supporting facility construction


The main body of the sewage tank has been poured, the top structure is waiting to be poured, and the anti-corrosion coating on the outer wall of the tank is under construction;


The main structure of the circulating water tank begins pouring concrete;


The main structure of the methanol tank area has started pouring concrete.